Maharashtra pollution board orders Adani Green unit to halt excavation at Sawarghar, second stop-work notice in a week

The Maharashtra Pollution Control Board (MPCB) has ordered Adani Renewable Energy One Ltd, a subsidiary of Adani Green Energy Ltd (AGEL), to stop excavation and construction at Sawarghar village in Patan taluka, Satara district. The notice was issued Nov. 20 by MPCB regional officer Kiran Hasabnis.
It is the second stop-work order in seven days against the 1,500 MW Tarali pumped storage project, estimated at Rs 5,675 crore.
What the pollution board found
The board's Satara sub-regional officer inspected the site and filed a legal action proposal the same day. According to the inspection report, excavation and development had begun at Gat Nos. 33 and 34 in Sawarghar for a temporary labour camp and storage, without notice to the board and without the required consents.
The report also said environmental clearance had not been obtained from the competent authority for that activity.
The directions were issued under Section 33A of the Water (Prevention and Control of Pollution) Act, 1974, and Section 31A of the Air (Prevention and Control of Pollution) Act. The board said work cannot resume without its prior approval and that violations will invite legal action.
Adani had said it bought private land in Sawarghar to set up temporary facilities, including a labour camp, for the Tarali project.
The village question
The MPCB acted a day after Rohan Bhate, Satara's honorary wildlife warden, wrote to MPCB Member Secretary Rahul Rekhawar on Nov. 19. Bhate alleged unauthorised large-scale excavation and construction at Sawarghar and asked for urgent intervention and an independent inquiry.
Bhate pointed out that the environmental clearance granted by the Union environment ministry on Feb. 11, 2025 covers 150.74 hectares across Nivade, Tondoshi, Kalambe and Jalu villages. Sawarghar is not on that list.
He also asked for a site inspection, an official panchnama recording the excavation, machinery and exact locations, and criminal action against those responsible if violations are established. Those are his requests. No charges have been filed.
The first notice: wildlife approval
On Nov. 13, the Satara Forest Department told the project manager to halt all work until prior approval is obtained from the National Board for Wildlife (NBWL). The department said an inspection found work under way at Tarale, which it described as falling in the deemed eco-sensitive zone of the Sahyadri Tiger Reserve. It demanded a written explanation within three days, along with documents on statutory approvals and tree-cutting permissions.
Adani Green contests that characterisation. In a Nov. 16 statement, the company said no part of the project falls inside a notified Protected Area and no forest land is involved. It said the site is private non-forest land about 3.2 km from the Koyna Wildlife Sanctuary, outside the notified buffer zone of the Sahyadri Tiger Reserve, and clear of any notified tiger corridor or eco-sensitive zone.
The company lists its approvals: a no-forest-land certificate dated Jan. 23, 2024, environmental clearance on Feb. 11, 2025, and a Consent to Establish from the MPCB on April 7, 2025. It says construction began only after the necessary approvals. Its wildlife clearance proposal is still under consideration by the NBWL.
The company's statement came before the MPCB notice, so it does not address the Sawarghar findings.
Rs 5,675 crore or Rs 56.75 crore
The larger dispute is about money. Wildlife conservation contributions for the Sahyadri Tiger Reserve are tied to project cost. At 4% of Rs 5,675 crore, the contribution comes to Rs 227 crore.
A notarised affidavit dated Sept. 8, 2026 listed the cost as Rs 56.75 crore, according to the complaint Bhate filed on the Prime Minister's grievance portal and the Maharashtra government's Aaple Sarkar portal. On that figure the total contribution would be roughly Rs 2.27 crore. After the state forest department accepted the lower figure, the initial deposit was set at Rs 56.75 lakh, with the rest due after NBWL approval.
Adani Green denies that the lower number was meant to cut its payment. The company says Rs 56.75 crore covered preliminary surveys, investigations, geological exploration and feasibility work, not a revised estimate for the whole project. It also says the State Board for Wildlife considered the project's cost to be Rs 5,675 crore.
The Union Ministry of Environment, Forest and Climate Change directed the Maharashtra Forest Department on Nov. 6 to investigate the discrepancy on priority. Following a Nov. 17 meeting with Adani Group officials, the state Forest Minister directed the company to fulfil all applicable regulatory and financial obligations.
What comes next
Three open items will decide how long Tarali stays stalled. The MPCB has a legal action proposal on file over Sawarghar. The NBWL has not ruled on the wildlife clearance. And the final decision on the cost discrepancy, which determines whether the conservation contribution is Rs 227 crore or Rs 2.27 crore, is pending.