Texas Environmental Regulator Resumes Data Center Permits After Abbott's Pause. Grid Hookup Freeze Remains

Since Gov. Greg Abbott ordered a pause on data center environmental permits in a Sept. 21 letter, the Texas Commission on Environmental Quality (TCEQ) has now lifted it. The agency is reviewing applications again, just weeks before Abbott hands the office to a Democrat who campaigned on freezing approvals.
What TCEQ did
TCEQ received notice Friday, Nov. 13, from Abbott's office that the state's grid operator had finished gathering information on community impacts from data centers. Abbott had made that a condition for restarting permits.
"The agency has resumed its normal permit review process and will evaluate applications under all applicable state and federal laws and regulations," TCEQ spokesperson Laura Lopez said in a written statement.
That was only one of several items Abbott gave the Electric Reliability Council of Texas (ERCOT) and electricity regulators in August. He also asked for an audit of every data center trying to connect to the grid, plus data on tax incentives, power use, water use and neighborhood effects. The same order froze new grid interconnections for data centers until the audit finishes.
That freeze has not been lifted. ERCOT's large-load connection halt is still in place pending the audit, and Abbott's office has not said when it will end.
3,500 megawatts in a day
Public Citizen, an advocacy group that has fought the permits, says TCEQ moved fast once the pause ended. In a Nov. 18 release, the group said the agency approved air permits for three data center gas plants totaling 3,500 megawatts on Monday, Nov. 16. It also said TCEQ quietly reactivated 17 construction approvals that had been suspended. TCEQ has not publicly confirmed those figures.
The suspended approvals trace back to October. Public Citizen and FracTracker Alliance noticed that some data center construction permits were still being cleared despite Abbott's order. TCEQ said it suspended those permits, then shut down its automated electronic filing system and required paper applications for staff review.
Kathryn Guerra, TCEQ watchdog campaign director at Public Citizen, called on the commissioners to resign. "The TCEQ is asserting that ERCOT has concluded its assessment of the community impacts of data centers, and without sharing those results with communities or detailing how the TCEQ will incorporate the findings into permitting decisions, agency leadership has begun unilaterally issuing data center permits," she said.
The objection is about process. Guerra's complaint is that the findings were not shared with the public, not that every permit is improper. TCEQ's stated position is that each application gets reviewed under all applicable state and federal law.
The political clock
Abbott lost reelection on Nov. 3 to Democrat Gina Hinojosa, who vowed on the campaign trail to keep data center approvals paused until the Legislature passes new state laws. She has also backed rules that would make developers carry more of the grid costs.
Neither Abbott's office nor Hinojosa's team immediately responded to the Texas Tribune's request for comment on the resumption.
The money at stake is large. Texas holds roughly a quarter of planned U.S. data center capacity through 2030. Jefferies counts at least 248 projects in the state and estimates that 13.3 gigawatts of announced development could be at risk under a Hinojosa moratorium. Goldman Sachs estimates that, come January, states led by Democrats who support extending AI construction moratoriums will hold 45% of planned U.S. data center capacity.
Brittany Kaiser, CEO of Alpha Compute, said the election has investors weighing other locations. "It makes us and our investors pause and think if we should be investing somewhere else," she told Fox News Digital. She added that projects with land, power agreements and capital already committed cannot easily move.
The largest players say they are largely insulated. CoreWeave says most of its Texas power capacity is already online, permitted or under construction. The company's third-quarter revenue rose 168%.
Grid rules already on the books
The Public Utility Commission of Texas approved an ERCOT "ride-through" rule that took effect in August. It requires large loads to stay connected during grid disturbances instead of dropping onto backup generators.
The rule responds to a July 22 event in Northern Virginia. A 230-kV line failed, and data centers drawing nearly 4 GW, close to 4% of PJM's load, disconnected together. Voltage and frequency spiked, and flickers were felt as far away as Chicago.
Alan Cooper, CEO of power infrastructure developer ON.energy, argues Texas's approach shows firm rules can protect reliability without stopping development. ERCOT estimates a loss of as little as 3.2 GW in West Texas could threaten reliability.
Two things will set the pace. One is the outcome of the ERCOT audit, which controls when new data centers can actually plug in. The other is whether Hinojosa, once in office, turns her campaign pledge into a formal moratorium, which she has said depends on legislators passing new laws. Permits issued in the meantime will not be easily clawed back.