PJM, CAISO and ISO New England File Data Center Grid-Connection Plans at FERC; SPP Due Friday

Grid operators have now put their data center plans in front of federal regulators. Most of the major ones filed by the Monday, Nov. 16 deadline, answering show-cause orders the Federal Energy Regulatory Commission issued on June 18.
ISO New England filed early, on Nov. 13. The Southwest Power Pool is scheduled to file by Friday, Nov. 20.
FERC's orders said the operators appeared to lack adequate rules for adding large loads. Each had to propose fixes or explain why its current rules were just and reasonable.
The agency named five problem areas:
- Efficient application and study processes, including alternative transmission technologies.
- Preventing cost shifts and making transmission costs transparent.
- Co-location and behind-the-meter generation.
- New transmission services for flexible large loads.
- A study process for generators serving "electrically proximate" large loads.
PJM: one-year study, new ride-through rules
PJM's centerpiece is a Fast Energization Process. It would study large load and generation requests together in a single one-year review, about twice as fast as the current process, according to PJM.
PJM's filing says the design targets slow interconnection, duplicative study tracks, speculative requests, little visibility into what drives transmission upgrades, and an ongoing resource adequacy shortfall. Donald Bielak, PJM's director of interconnection planning, told FERC it is "the next evolution of PJM's interconnection process."
PJM's transmission owners filed their own tariffs covering rates, cost allocation, cost recovery and financial protections. PJM also addressed co-location and behind-the-meter rules in the same package.
A separate PJM filing deals with reliability. It would require large computational loads to ride through voltage and frequency disturbances rather than disconnecting. PJM proposed an effective date of Jan. 16, 2027.
The July 22 event behind the rule
The trigger was July 22 in the Dominion transmission zone of Northern Virginia. A mechanical failure took a 230-kilovolt line out of service at 7:56 a.m. Utility protection cleared the fault normally.
The voltage dip was enough to send data center equipment to onsite generators and batteries. Nearly 3.9 GW of load left the grid at once, the largest such transfer in PJM's history. An initial 2,970 MW drop was followed by another 1,099 MW.
PJM's system load fell from 99,984 MW to 96,205 MW. Frequency rose to 60.092 hertz and local voltages hit 1.138 per unit. PJM's Control Center managed the event safely, the grid operator said, though it described the scale and speed as a serious threat to reliability. PJM says the proposed standards would have mitigated the impacts had they been in place.
The filing defines a Large Computational Load as 50 MW or more. PJM already serves around 10 GW of such load and forecasts up to 30 GW by 2030. PJM says it will keep working with stakeholders on ramp-rate requirements and other performance standards.
ISO New England and California
ISO New England's filing, docket ER27-484-000, creates three new transmission services for large loads. It adds operating requirements for forecasting, telemetry, communications, ramp rates and outage coordination.
It also proposes a price-based redispatch mechanism for non-firm service, triggered at $250 per megawatt-hour. A bring-your-own-new-capacity requirement and a Cost Recovery Agreement are meant to keep transmission costs from landing on other customers. The proposed schedule is June 1, 2027 for the application and study process and June 1, 2028 for the new services.
California ISO's board approved its package on Oct. 28. It includes an interim connection pathway so eligible large users can receive service while required transmission upgrades are still being built. In its filing, CAISO said the changes "strengthen accountability and protect existing customers." It also cited protection against speculative development.
The cost question
The filings arrive amid a surge in data center development and growing pushback. Part of that pushback is the concern that existing utility customers will end up paying for some of the electric infrastructure built for data centers. FERC's own list of issues names cost shifts and transparency into transmission costs.
CAISO and ISO New England both say their proposals address that risk. Whether the tariff language does so is FERC's call.
The underlying backlog is large. S&P Global counted 1,740 GW of projects awaiting grid connection as of June, more than the existing U.S. generating fleet, according to a Nixon Peabody analysis. Projects that reach commercial operation have recently taken about five years from request to operation.
The same analysis notes that FERC's earlier interconnection rule, Order No. 2023, moved toward cluster studies and stricter readiness requirements. Developers should still expect timing and cost uncertainty while those processes take hold, it says.
What comes next
SPP's filing is due Friday, Nov. 20. After that, FERC must decide for each region whether the proposed tariff revisions answer its June concerns. PJM's ride-through rule carries a proposed Jan. 16, 2027 effective date, and that date depends on FERC's action.