Norway halts new data center grid reservations as developers hunt used gas turbines

Norway has hit pause on new power hookups for data centers. Statnett AS, the country's grid operator, said in a statement Monday, Nov. 9, that it will suspend further reservation of electricity connections for them while the country works out how to handle the load. The halt is expected to end no later than Aug. 1, 2027.
Statnett says about 800 megawatts of data centers are currently connected to the Norwegian grid.
The same squeeze is showing up in the U.S., where the problem is turbines rather than wires.
The turbine backlog
Worldwide gas turbine orders top 100 gigawatts, according to Wood Mackenzie. Global manufacturing capacity is an estimated 60 to 70 GW a year.
"Delivery conversations (are) firmly focused on the 2030 to 2031 window," Aurora Tenorio, a senior analyst at Wood Mackenzie, said of the U.S. market.
Jefferies analysts estimate U.S. data centers account for nearly 17 GW of demand this year, and that the figure could more than triple by 2028. Manufacturing capacity is expected to reach about 87 GW in 2028. Expected turbine power demand that year is 129 GW.
The global turbine market is worth roughly $25 billion a year. Until a few years ago it served almost exclusively traditional utilities.
The secondhand scramble
With new orders stretching into the next decade, buyers are going shopping elsewhere. More than a dozen brokers, service firms and suppliers told Reuters that utilities and developers are reviving mothballed machines and converting retired jet engines.
"That secondary market is very, very hot right now," said Ana Amicarella, CEO of equipment services firm EthosEnergy. "We also have seen an escalation on the prices of what people are demanding."
Reuters' analysis put well-maintained used units at about $1.5 million to $1.7 million per megawatt, and refurbished units around $1.3 million. New turbines run $2 million to $2.5 million per megawatt.
The sharpest example Reuters cited: two 14.5-megawatt turbines from Caterpillar subsidiary Solar Turbines sold for $12.5 million, or about $430,000 per megawatt. A new equivalent would have cost around $35 million and taken five years.
But Noor Qureshi, an associate at Enverus Intelligence Research, says the used market can only help partly. "The market is already constrained, with limited excess supply, so it is unlikely to offset a meaningful share of the delays," she said. Air permits and grid access are also holding projects up. No reliable estimate exists for how much the secondary market adds to supply.
Crusoe's bets
AI infrastructure firm Crusoe shows how scattered the strategy has become. It signed a contract with ProEnergy on April 16, 2026, for 13 PE6000 aeroderivative gas turbine generators. Each is rated at 50 MW, for 650 MW total. Delivery is expected by summer 2027.
The PE6000 is built on the core of a GE CF6-80C2 jet engine. Crusoe has also placed an order with GE Vernova for about 29 LM2500XPRESS packages totaling nearly 1 GW.
Not every order survived. In September 2026, Crusoe canceled a $1.25 billion order with Boom Supersonic for 29 of its Superpower turbines. Crusoe said it "will continue to use turbines, but not Boom's."
xAI is on the same path. According to reporting by the New York Times, drawing on state permit records and satellite imagery, xAI has installed eight converted turbines in Mississippi to power its Colossus 2 data center. The Times reported that such converted units are less efficient and emit more than turbines designed purely for power generation.
Separately, the Financial Times reported Sunday that Anthropic bought commitments for 1.7 GW of heavy-duty natural gas generators from Texas-based OnePWR Solutions in late September, in a deal valued at about $3.4 billion. That figure is the Financial Times' reporting. The deal reportedly also covers engineering and construction capabilities. Anthropic did not acquire OnePWR or its employees, the report said.
Local opposition
Not everyone wants the buildout at all. Louisiana Gov. Jeff Landry, a Republican, pushed back Sunday on Fox News' "The Sunday Briefing" against opposition to data centers. "Do we want good paying jobs or do we wanna see those jobs offshored again?" he asked. He called the facilities "digital factories" and said their water and electricity needs can be managed responsibly.
Pressed on a voter survey showing 76% opposed a new data center in their community, Landry pointed to results in Richland Parish. "You didn't run that poll in Richland Parish," he said, citing higher teacher pay and new economic opportunities.
What is physically fixed
The constraint is steel, factory slots and permits. Money is not the limit. Crusoe and its peers can sign checks, but a turbine ordered today is quoted for 2030 or later, and a jet engine only converts so many times.
Norway chose to ration grid access. U.S. developers are bidding against each other for whatever machines already exist.
Two dates now frame the test. Statnett's reservation halt is set to lift no later than Aug. 1, 2027. Crusoe's ProEnergy turbines are due by summer 2027. Whether that delivery holds, in a market where new units are quoted six years out, will show how fast the converted-engine route can actually move.