Texas Resumes Data Center Permit Reviews, Issues SpaceX Air Permit Weeks Before ERCOT Audit Is Due

Texas environmental regulators are back to reviewing data center permits. The pause Gov. Greg Abbott ordered this fall is over, and the first big approval has already landed.
The Texas Commission on Environmental Quality received notice on a Friday from Abbott's office that officials at the state grid operator had finished gathering information on community impacts from data centers. "The agency has resumed its normal permit review process and will evaluate applications under all applicable state and federal laws and regulations," TCEQ spokesperson Laura Lopez said in a written statement.
The SpaceX permit
On a Monday, TCEQ issued SpaceX an air permit for a planned data center and gas-fired power plant in the Rio Grande Valley, a $24 billion project. Lopez confirmed the permit was issued.
The permit covers 35 natural-gas turbines with a combined 750 megawatts of capacity on a 444-acre site. The off-grid plant may emit up to 248 tons of smog-forming nitrogen oxides a year. The threshold for stricter review, which includes a public hearing, is 250 tons.
The approval came three days after FracTracker Alliance and Public Citizen complained that SpaceX had begun construction without a permit, which they said could violate the Clean Air Act. Their submission included satellite and aerial images they say show construction between October 9 and November 12, including cranes installing gas-powered turbines. TCEQ did not respond to the complaint.
SpaceX's position is that the Clean Air Act allows turbines to operate for a year without permits. Elon Musk told investors last month that the company plans to expand its AI computing capacity by 10 to 20 gigawatts next year.
What ERCOT says
Abbott's pause rested on a specific condition. His Sept. 21 letter told TCEQ to wait until the Electric Reliability Council of Texas "completes its review." On Oct. 23, he wrote to TCEQ's acting director that the pause covered air-emissions permits and water-rights approvals.
ERCOT has not said that review is finished. Spokesperson Trudi Webster said Monday evening that the audit is still underway and that results are planned for Dec. 10. ERCOT has told the Public Utility Commission it will file two reports by that date: one on which large loads of 75 megawatts and up remain eligible for its Batch Zero interconnection study, and one summarizing water, power, ownership and community-impact information. Both are slated for discussion at the PUC's Dec. 17 open meeting, according to a client alert from the law firm Gibson Dunn.
As of ERCOT's Nov. 5 update, it had reviewed first-round responses from 257 developers, roughly 5,140 questions. A shorter second round of developer-specific questions was expected, and ERCOT said its review was not complete. At that same update, ERCOT reported receiving responses from 93% of 465 projects, enough for "a statistically meaningful analysis for the final report."
So the state's position is that the community-impact information-gathering step is done. The grid operator's position is that the broader audit is not. Neither Abbott's office nor Hinojosa's media team immediately responded to requests for comment on Tuesday.
Critics want answers
Public Citizen called on TCEQ's commissioners to resign. "The TCEQ is asserting that ERCOT has concluded its assessment of the community impacts of data centers, and without sharing those results with communities or detailing how the TCEQ will incorporate the findings into permitting decisions, agency leadership has begun unilaterally issuing data center permits," said Kathryn Guerra, the group's TCEQ watchdog campaign director.
The pause was already leaky. An October analysis by Public Citizen found TCEQ had advanced or issued 17 data-center-related permits during the pause, mostly for stormwater and water quality. TCEQ said it suspended those permits, then shut down its automated electronic filing system and required physical applications.
A political clock
Data centers were a dominant issue in the election. Opposition has been growing all year across Texas, with Democrats and Republicans alike worried about grid stability, pollution from new gas generation, and water use in a state with serious drought concerns.
Abbott lost his Nov. 3 reelection bid to Democrat Gina Hinojosa. She campaigned on keeping data center approvals paused until the Legislature passes new laws. "We will have laws to protect Texans, and we need to stop what we are doing with data centers until we have those protections," she told CNN's Jake Tapper in an interview on a Thursday that week.
She has also framed it as compatible with growth. "We have always been a pro-business state in Texas, but what changes now with me as governor is it has to be a partnership that benefits Texans," Hinojosa said.
The Legislature is moving too. Bill filing for the 90th Legislature opened Nov. 9, and bipartisan proposals have already been filed to repeal the data center sales tax exemption, require water-use disclosure, and bar local tax incentives, according to Gibson Dunn. Democrats will hold the governorship and the House, Republicans the Senate.
Hinojosa does not take office until Jan. 19, 2027. Until then, Abbott remains governor, and TCEQ's reviews continue. The next fixed dates are ERCOT's Dec. 10 audit filings and the PUC's Dec. 17 meeting. What remains unanswered is whether TCEQ will publicly explain how the audit findings feed into permits it is already issuing.