PJM Clears 715 Power Projects, Over 200 Gigawatts, in First Reformed Interconnection Cycle

PJM Clears 715 Power Projects, Over 200 Gigawatts, in First Reformed Interconnection Cycle
PJM Interconnection, which runs the grid for 65 million people across 13 states plus DC, just moved 715 proposed power projects into active study under a new first-ready, first-served process. That's more than 200 gigawatts of potential capacity, but PJM's own numbers show most projects that apply never actually get built.

PJM Interconnection announced that 715 new generation projects have qualified for study under the first cycle of its reformed interconnection process. Combined, those projects claim the potential to generate more than 200 gigawatts of electricity, according to PJM.

That's the queue that manages grid connections for the largest wholesale electricity market in the country, covering all or part of 13 states and Washington, D.C.

The application window closed April 27 and drew 811 total proposals. After PJM's initial screening for technical documentation and financial deposits, 715 made it through to the study phase, PJM said.

This is the first batch processed under PJM's new "first-ready, first-served" model. The old system let developers file speculative projects with little skin in the game, clogging the queue with proposals that never got built. The new rules require proof of site control and up-front financial commitments before a project even enters the cycle study process.

"PJM is encouraged at the number and quality of applications that are proceeding through the study process to help address the long-term shortage of electricity supply that we are facing," said Jason Connell, PJM's Vice President of Planning. "The rigorous process that is now in place is designed to encourage projects that will get built."

The Math Problem Nobody Should Ignore

Since 2020, PJM has processed more than 300 GW worth of projects. Of that, only about 100 GW ended up with signed interconnection agreements, according to PJM's own data.

And even that overstates what's actually online. PJM currently has 51 GW of generation with signed agreements, but the grid operator itself says many of those projects are either not being built at all or are getting stalled by state permitting delays and supply chain backlogs.

The 200 GW figure from Cycle 1 should be viewed with skepticism. Historical performance says only a fraction of these 715 projects will ever generate a watt of power for the grid. PJM's own track record demonstrates this point.

Why This Matters: Data Centers Are Eating the Grid

PJM projects electricity demand could rise by up to 70 GW by 2038, driven mostly by data centers and other large industrial load customers. That's an enormous jump, and PJM says demand growth is currently outpacing new supply.

That imbalance is the whole reason for the queue reform. A grid operator sitting on a pile of unbuilt speculative projects while data center demand explodes is a recipe for blackouts and price spikes. PJM has been explicit that the old process was too slow and unpredictable to keep up.

The reformed cycle is designed to run one to two years per project, depending on complexity, and PJM says there is currently no backlog remaining from prior queues. That's a real operational improvement if it holds.

The Tools Behind the Screening

PJM is leaning on new technology to move faster, including HyperQ, an AI-enabled tool built by Google's Tapestry unit to process large volumes of application data. PJM says it will evaluate the tool's performance throughout this first cycle.

Whether an AI tool built by a Google subsidiary can meaningfully speed up grid interconnection studies, which involve enormously complex engineering analysis of transmission impacts, is an open question. PJM hasn't published results yet because the cycle just started.

What's Actually in the Queue

PJM's release breaks out project types but groups several technologies into a catch-all "other" category covering biomass, coal, fuel cell, fusion energy, and methane. That's an odd mix to lump together, and it means the public doesn't get a clean picture of how much, if any, new coal or fuel-cell capacity is actually being proposed versus wind, solar, gas, and battery storage projects that presumably make up the bulk of the 715.

PJM did not break out gigawatt totals by individual fuel type in the material it released, which limits how precisely anyone can assess whether this queue actually addresses the reliability concerns PJM says are driving the reform. Firm, dispatchable capacity, like natural gas plants, matters more for grid reliability than intermittent renewable capacity. Without a full fuel-type breakdown, it's hard to judge whether these 715 projects will genuinely solve PJM's supply shortfall or mostly add more weather-dependent generation to a grid that increasingly needs power on demand.

PJM fixed a real bureaucratic problem by forcing developers to put money and land control on the table before wasting study resources. That's a sensible reform. But the headline number of 200-plus gigawatts is a ceiling, not a promise, and PJM's own history says the real number that reaches the grid will be a fraction of that. The next checkpoint will be when PJM completes this first cycle study, expected within one to two years, and reports how many of these 715 projects actually sign interconnection agreements.

Sources used for this briefing

This briefing was written by UBH's AI agent — these are the reporting inputs it draws on, linked so you can verify.

center
Power EngineeringPJM accepts over 700 generation projects in new ‘first-ready, first-served’ queue