LBNL Update Puts Data Centers at 11.8% of US Electricity by 2030, and a Harvard-Led Study Finds 403 Hyperscale Sites Used Michigan-Sized Power

Since Howden's analysis put data center power growth at 19% a year against 2% for grid capacity, the underlying consumption numbers have come into sharper focus. They are bigger than the early AI-boom forecasts, and they are less tidy than the headlines suggest.
The federal lab's updated forecast
Lawrence Berkeley National Laboratory (LBNL), working with Department of Energy support, estimated that US data centers used 176 terawatt-hours (TWh) in 2023. That was about 4.4% of US electricity. The same facilities drew 58 TWh in 2014.
Its December 2024 report projected 325 to 580 TWh by 2028, or 6.7% to 12% of national consumption. In capacity terms, that is 74 to 132 gigawatts of average power. LBNL converts to gigawatts by assuming 50% utilization.
A 2025 update, published in June 2026, raised the baseline. It puts 2024 US data center use at 192 TWh, or 4.7%. Its 2030 reference case is 649 TWh, or 11.8% of US electricity.
Sensitivity analyses widen that to between 521 and 843 TWh, or 9.5% to 15.3% of national demand. LBNL itself cautions that projections are "inherently less certain than historical estimates."
The reports estimate a gap of more than 100 GW between what data centers will need and what utilities plan to add through 2030.
Michigan-sized, and mostly fossil
A separate Harvard-led study tried to measure actual draw rather than forecast it. Researchers used satellite imagery to verify the locations of 403 hyperscale data centers, then used power-plant records to estimate emissions.
They found those facilities used between 68 and 99 TWh in the year ending April 2025. That is about 1.8% of US electricity. At the high end, it is close to what Michigan or Tennessee consume in a year.
About 54% of that electricity came from fossil fuels: roughly 38% natural gas and 15% coal. The team estimated 25.7 million metric tons of carbon dioxide, more than Denmark's emissions over the same period.
Virginia alone accounted for about a quarter of the electricity in the study. Add Oregon, Ohio and Iowa, and those four states make up more than half.
Gianluca Guidi, a Harvard biostatistician and the study's lead author, said: "Data centers are growing incredibly fast, driven largely by AI, and decisions about where to build them and how to power them are being made right now."
The study's figures cover only hyperscale sites. Facility-level data is rarely public, so the team estimated each site's capacity and cooling load from assumptions. That explains why 1.8% sits so far below LBNL's 4.7% for all US data centers.
Why the numbers do not match
The figures people quote measure different things. Geography, scope (all data centers, AI only, or named operators), IT load versus total facility load, and the denominator behind any percentage all change the answer.
The International Energy Agency puts US data centers at about 180 TWh in 2024, nearly 45% of the world total of roughly 415 TWh. The IEA labels its historical figures "modelled estimates, not measured data."
None of these is a meter reading for the whole sector. They are estimates with different boundaries.
Off-grid power and the delay math
Howden estimates data centers took about 5% of US grid capacity in 2025. To hold that share through 2030 at current growth, they would have to source up to 58% of their power off the grid, roughly 110 GW. Howden itself considers that unlikely.
Rob Gramlich, president of Grid Strategies, told Fortune in September there is a "mismatch in timing" between how fast data centers want power and how fast the grid can expand. After about 25 years of flat demand, he said, utilities "got out of practice on building new infrastructure."
Kathryn Burke, who leads US specialty energy and power growth at Marsh, told Fortune she expects "around 50% to 60% of data center projects to be delayed beyond the one-to-two-year timelines developers are counting on."
The ratepayer and voter pushback
A Cornell University study in Nature Energy found data centers paid only 38% of the infrastructure costs tied to their growth in 2025, $3.12 billion of an $8.25 billion bill. The rest fell to other ratepayers.
Voters have noticed. Fortune counted 40 of 41 local ballot measures rejecting data center development on Nov. 3. A University of Pennsylvania Annenberg Public Policy Center survey this summer found 70% of adults under 30 oppose new data centers in their area, against 61% of all adults.
Elijah Lee of Voters of Tomorrow told Fortune: "The idea of now having to grow up and compete in terms of water prices and energy prices with a tech company is not something I can say I'm excited about."
The money behind the buildout is not in dispute. Citigroup projects Big Tech will spend more than $2.8 trillion on AI infrastructure through 2029, and a Brookings study puts US investment at $10.3 trillion between 2025 and 2032.
It is an open question how much of the 100-plus GW shortfall gets built, and how much of it lands on ratepayers. Marsh's expectation that half or more of projects will slip past their timelines is the next test of the 2030 forecasts.