Fed Counts $680 Billion in AI Computing Debt Issued Through October as Blackstone's QTS Cuts Debt Sale by About 60%
The Federal Reserve's Nov. 13 Financial Stability Report puts AI-related borrowing at about 31% of nonfinancial investment-grade issuance, up from under 6% in 2023. Separately, Blackstone-owned data center operator QTS raised roughly $300 million of a planned $800 million debt sale, according to Bloomberg. QTS's remaining $200 million bank loan still has to be priced.

The spotlight on AI has moved from share prices to the debt financing the build-out. Two items point the same direction: the Federal Reserve's latest numbers on that debt, and a data center borrower that could not sell all of what it offered.

What the Fed counted

The Fed's Financial Stability Report, released Friday, Nov. 13, says debt issued to finance advanced computing topped $680 billion through October 2026. That is roughly five times the $130 billion issued in all of 2023.

The borrowing now makes up about 31% of nonfinancial investment-grade corporate debt issuance this year, up from under 6% in 2023. The Fed estimates outstanding public debt tied to advanced computing at more than $1.1 trillion. Issuance is a one-year flow and outstanding debt is a stock, so the two numbers do not add together.

The larger exposure sits off the usual debt tallies. For seven companies (Amazon, Alphabet, Broadcom, Meta, Microsoft, Nvidia and Oracle), the Fed found more than $1 trillion in data center leases that have not yet started. It also found more than $2 trillion in take-or-pay contracts and residual value guarantees.

The Fed says those figures are not discounted and are "not directly comparable with on-balance-sheet debt, which is discounted." Even so, the report says these obligations "have grown even more rapidly" than debt.

The mechanism, in the Fed's words: hyperscalers sign long-term leases with third-party developers, and "these leases are then used by the third-party developers to secure financing for the data center's construction."

The report also says the largest U.S. bank holding companies have close to $1 trillion of exposure to large technology firms, data center developers, advanced computing special-purpose entities, private credit vehicles and utility companies. It flags hedge fund leverage at its highest level since 2013, concentrated in a small group of funds. The Fed's information is current as of Oct. 28.

The survey

The report also carries the New York Fed's fall survey of 23 market contacts. About 87% named AI as a salient risk to U.S. financial stability, up from 50% in the spring. That works out to roughly 20 respondents. The report states the survey reflects respondents' views, not those of the Fed Board or the New York Fed.

The survey closed before Nvidia announced on Nov. 12 that CEO Jensen Huang had resigned effective immediately. Nvidia is one of the seven companies in the Fed's tally.

The Fed's own caveat

The Fed is not predicting a crash. The report says the largest technology firms "may absorb losses in the event of a future downturn, mitigating their effects on the rest of the financial system." It adds that their "economic exposure to such a downturn may be substantially larger than suggested by their on-balance-sheet liabilities."

The report describes the web of public credit, private lenders and special-purpose vehicles behind data center construction as creating "vulnerabilities that necessitate close monitoring."

QTS falls short

Bloomberg reported, citing its own sources, that QTS cut a planned private debt sale by about 60%. The operator raised roughly $300 million instead of the $800 million it sought. Blackstone acquired QTS in 2021 for $10 billion.

The offering launched Oct. 26 through QTS Thunder Managing Issuer LLC, with Mizuho, Natixis, SocGen and Wells Fargo arranging notes of seven to 15 years. What got done Friday was a $100 million seven-year private placement at 245 basis points over benchmarks. A $200 million five-year bank loan still has to be priced over the coming weeks.

According to Bloomberg's sources, some investors disliked the pricing, and QTS declined to pay much higher yields to draw them in. Others could not take more because QTS has already tapped the private placement market several times.

For comparison, initial price talk on QTS's first green project bond in April, a 10-year rated Baa2 by Moody's, was around 162.5 basis points, according to ZeroHedge. The two deals differ in tenor and structure, so the roughly 80-basis-point gap is a rough guide rather than a like-for-like measure.

Blackstone's exposure to QTS

BREIT, Blackstone's real estate income trust, has directed $9.1 billion into data center projects with QTS. By late September, QTS made up 29% of BREIT's real estate asset value, according to Crypto Briefing.

In June, Blackstone-managed funds sold stakes in three Northern Virginia data centers to Digital Realty for $3.5 billion. The assets were fully leased to investment-grade tenants and carried a gross valuation of $7.8 billion.

A social media claim that BREIT will buy Amazon data centers for $5 billion has no public confirmation. No announcement or filing from Blackstone or Amazon supports it.

Nothing in the sources establishes that QTS's shortfall resulted from the Fed's findings or from the Huang resignation. The Fed report is a snapshot as of Oct. 28, and the QTS offering launched two days before that date. Both are data points on the same market.

Moody's has warned that weaker borrowers may struggle to refinance loans maturing in 2027 to 2029, according to Reuters. The next test is QTS's $200 million bank loan, which has yet to price.

Sources used for this briefing

8 links from 8 independent newsrooms (syndicated copies of the same report count once)

These are the sources it draws on, linked so you can verify.

center
Crypto BriefingBlackstone REIT’s reported $5B Amazon data center deal remains unconfirmed
left
edition.cnnThe real question we should all be asking about AI | CNN Business
right
ZeroHedgeFirst Junk, Now Investment Grade: Blackstone's Own Data Center Giant Can't Sell $800 Million Of Debt
unknown
The AI Consulting NetworkFed: $1 Trillion in Unstarted Data Center Leases
unknown
economy.ac“AI Rally Hit by Midterm Election Shock and Nvidia Setback” Fed Warns of Risks From Debt-Linked Investments
unknown
AI WeeklyFed Survey: 87% of Contacts Name AI Top Stability Risk
unknown
Tech TimesFed Financial Stability Report: AI Data Center Debt Hits 31% of Investment-Grade Issuance - Tech Times
unknown
iafricaUS Federal Reserve Names AI as Top Financial-Stability Risk as Data-Centre Debt Soars